Cost Estimates
The following Class D cost estimates are based on the proposed plan and are for initial budgetary discussions only. These opinions of probable costs are presented on the basis of experience, qualifications and best judgment. Market trend changes, unknown environmental hazards, non-competitive bidding situations, unforeseen labour and material adjustments may have an impact on final costing. All values are provided in 2019 dollars. HST is not included.
Signage
Directional |
x |
10 |
$600 (ea) |
= |
$6,000 |
Small Trailhead |
x |
3 |
$800 (ea) |
= |
$2,400 |
Large Trailhead |
x |
4 |
$1000 (ea) |
= |
$4,000 |
Design Fees |
= |
$3,600 |
|||
Subtotal |
= |
$16,000 + HST |
Trail Recapitalization
Existing Trail right-of-way clearing |
x |
880 m |
= |
$4,400 |
Remediate informal trails |
x |
470 m |
= |
$3,525 |
Subtotal |
|
|
= |
$7,925 + HST |
Trail Capitalization
Low ground puncheon walk |
x |
30 m |
= |
$5,250 |
New Trail |
x |
436 m |
= |
$6,540 |
New Access Point |
x |
170 m |
= |
$3,400 |
Gravel |
= |
$8,650 |
||
Subtotal |
= |
$23,840 + HST |