The following Class D cost estimates are based on the proposed plan and are for initial budgetary discussions only. These opinions of probable costs are presented on the basis of experience, qualifications and best judgment. Market trend changes, unknown environmental hazards, non-competitive bidding situations, unforeseen labour and material adjustments may have an impact on final costing. All values are provided in 2019 dollars. HST is not included.

Signage

Directional

x

   10

$600 (ea)

=

$6,000

Small Trailhead

x

    3

$800 (ea)

=

$2,400

Large Trailhead

x

    4

$1000 (ea)

=

$4,000

Design Fees

=

$3,600

Subtotal

=

$16,000 + HST

 

Trail Recapitalization

Existing Trail right-of-way clearing

x

880 m

=

$4,400

Remediate informal trails

x

470 m

=

$3,525

Subtotal

 

 

=

$7,925 + HST

 

 

 

 

Trail Capitalization

Low ground puncheon walk

x

30 m

=

$5,250

New Trail

x

436 m

=

$6,540

New Access Point

x

170 m

=

$3,400

Gravel

=

$8,650

Subtotal

=

$23,840  + HST